Project Details
- Rob’s house
- Industrial
- Marafiq
- Yanbu
- October 2007
- November 2008
Project Description
The project involved the partial replacement of the force main line between IW 11 and IW 13 in Yanbu.
The works included the installation of a 1,000 mm diameter GRP pipeline and 1,000 mm diameter butterfly valves, as well as the construction of a concrete valve room and the execution of excavation, backfilling, and dewatering works.
Project Scope
The project scope covered pipeline replacement, valve installation, concrete works, and the associated civil and groundwater-control works required for the force main line.
Civil Works
Site preparation, structural works, road and parking perimeter.
Electromechanical
MEP works and installation of power IT/data systems.
External Utilities
Perimeter fence and external utility works.
Project Delivery Scope
Partial replacement of the force main line
Installation of 1,000 mm GRP pipeline
Installation of 1,000 mm butterfly valves
Construction of concrete valve room
Excavation and backfilling works
Dewatering works
Associated civil works