SADARA – ERB

01-sadara-erb

Project Details

  • SADARA – ERB
  • SADARA (Saudi Aramco Dow Arabia) Chemical Co.
  • Industrial
  • SADARA Petrochemical Plant, 2nd Industrial City, Jubail, KSA
  • July 2013
  • December 2017

Project Description

The project involved the construction of a 4,000 m² one-story pre-cast blast-proof building consisting of a fire department, medical center, and security center, supporting emergency shutdown operations at SADARA Petrochemical Plant.

The project included reinforced concrete structure works, steel structure works for the garage area, which can hold up to six fire trucks, and precast panels. The works were delivered with high safety and quality standards, using advanced planning and control practices.

07-sadara-erb
06-sadara-erb
05-sadara-erb
04-sadara-erb
03-sadara-erb
02-sadara-erb

Building Works

Pre-cast blast-proof building, reinforced concrete structure, steel garage area, and precast panels.

Electromechanical

Firefighting system, HVAC duct system, BMS, communication system, and chilled water.

Commissioning Works

Pre-commissioning and commissioning packages to support initial client operations.

Project Delivery Scope

Construction of blast-proof emergency response building
Fire department, medical center, and security center
Reinforced concrete and steel structure works
Precast panel installation
Firefighting, HVAC, BMS, and communication systems
Chilled water and radioactive bunker storage
Pre-commissioning and commissioning support
Architectural works