MANIFAH FIELD CAUSEWAY

MANIFAH_FIELD_CAUSEWAY_01

Project Details

  • MANIFAH FIELD CAUSEWAY
  • Jan De Nul and Saudi Aramco
  • Industrial
  • Manifah Field Causeway
  • May 2007
  • January 2008

Project Description

The project involved the construction of temporary camp and site facilities at Manifah Field Causeway.

The works included earthworks, cut and fill, marl and base course compaction, asphalt works, fabrication, supply and erection of 22,000 m² prefab units for Aramco and JDN camp and offices, including support facilities such as kitchen, recreation, gymnasium, mosques, furniture, equipment, A/C works, utilities, electrical works, water network, sewer network, data and telecommunication works, MATV system, plantation and irrigation, sport facilities and sport area.

MANIFAH_FIELD_CAUSEWAY_02
MANIFAH_FIELD_CAUSEWAY_05
MANIFAH_FIELD_CAUSEWAY_04
MANIFAH_FIELD_CAUSEWAY_06
MANIFAH_FIELD_CAUSEWAY_03
MANIFAH_FIELD_CAUSEWAY_01

Site Facilities

Temporary camp facilities, prefab units, offices, kitchens, recreation areas, gymnasium, and mosques.

Utility Networks

Water network, R.O. plant, sewer network, sewage treatment plant, pipes, pumps, tanks, and lift station.

External Works

Earthworks, asphalt, plantation, irrigation, sport facilities, and external site preparation works.

Project Delivery Scope

Construction of temporary camp and site facilities
Fabrication, supply, and erection of prefab units
Camp and office support facilities
A/C, utilities, and electrical works
Water network and R.O. plant
Sewer network and sewage treatment plant
Data, telecommunication, and MATV systems
Plantation, irrigation, and sport facilities