Project Details
- HARAD GAS PLANT
- Tecnicas Reunidas / Saudi Aramco
- Industrial
- Harad
- May 2018
- July 2019
Project Description
The project involved the construction of site facilities for Tecnicas Reunidas, including 17,000 m² of camp and main office facilities.
The works included site preparation, fences and gates, asphalt and walkways, furniture and HVAC, and complete utilities including water networks, firefighting networks, power networks, fire alarm systems, piping, tanks, cables, lighting, generators, pumps, and related works.
Site Facilities
Camp facilities, main offices, warehouses, refrigerated stores, furniture, and HVAC.
Utility Networks
Water, firefighting, power, fire alarm, piping, tanks, cables, lighting, generators, and pumps.
External Works
Site preparation, fencing, gates, asphalt works, and walkways.
Project Delivery Scope
Construction of camp and main office facilities
Construction of steel-structure warehouses
Closed refrigerated store facilities
Site preparation and external works
Fence, gates, asphalt, and walkways
Furniture and HVAC works
Complete utility networks
Fire alarm, lighting, generators, pumps, and related systems