Saudi Aramco Camp And Offices – Shayba

SAUDI_ARAMCO_CAMP_AND_OFFICES_SHAYBA_04

Project Details

  • Saudi Aramco Camp And Offices – Shayba
  • Saudi Aramco
  • Temporary Facilities
  • Shayba, KSA
  • July 2011
  • October 2012

Project Description

The project involved the construction of permanent facilities for the Saudi Aramco Project Management Team (SAPMT), including an accommodation camp for 780 occupants and offices at Shayba, KSA.

The works included Sabkha 113 accommodation camp, offices at Sabkha 112, STP, lift station with a capacity of 6,500 m³/day, 2,000 m³ water tanks, evaporation ponds, and all required power generation. The scope also included services for offices and common facilities for three years.

SAUDI_ARAMCO_CAMP_AND_OFFICES_SHAYBA_06
SAUDI_ARAMCO_CAMP_AND_OFFICES_SHAYBA_05
SAUDI_ARAMCO_CAMP_AND_OFFICES_SHAYBA_03
SAUDI_ARAMCO_CAMP_AND_OFFICES_SHAYBA_02
SAUDI_ARAMCO_CAMP_AND_OFFICES_SHAYBA_01
SAUDI_ARAMCO_CAMP_AND_OFFICES_SHAYBA_04

Site Facilities

Permanent facilities, accommodation camp, SAPMT offices, and common facilities.

Utility Systems

STP, lift station, water tanks, evaporation ponds, and power generation.

Operations Support

Three-year services for offices and common facilities.

Project Delivery Scope

Construction of permanent facilities
Accommodation camp for SAPMT
Offices at Sabkha 112
STP and lift station works
Water tanks and evaporation ponds
Required power generation
Three-year services for offices
Common facilities support