Construction of 45 Imam Villas

06_construction_of_45_immam_villas

Project Details

  • Construction of 45 Imam Villas
  • Royal Commission of Jubail and Yaanbu
  • Others
  • Jubail, KSA
  • October 2021

Project Description

The project involved the construction of housing units in Jubail, with a total quantity of 45 villas distributed across 23 lots.
Each villa had an average area of 280 m². The works included site preparation for all sites, excavation, backfilling, hardscape and landscape works, concrete works, block works, plastering, painting, finishing works, parking areas, and all MEP works.

01_construction_of_45_immam_villas
02_construction_of_45_immam_villas
03_construction_of_45_immam_villas
04_construction_of_45_immam_villas
05_construction_of_45_immam_villas
06_construction_of_45_immam_villas

Residential Construction

Construction of 45 housing villas distributed across 23 lots in Jubail.

Civil & Finishing Works

Site preparation, concrete works, block works, plastering, painting, tiles, doors, windows, and handrails.

MEP Works

Lighting, plumbing, fire alarm, HVAC, power, and firefighting systems.

Project Delivery Scope

Construction of housing villas
Site preparation for all sites
Excavation and backfilling works
Hardscape and landscape works
Concrete sub-structure and super-structure works
Block, plastering, painting, and finishing works
Tiles, doors, windows, and handrails
Parking areas
Lighting, plumbing, HVAC, and power works
Fire alarm and firefighting systems